Project Description

Roy Hill Project – Flush Butt Yard
Fremantle Constructions/John Holland
October 2013

Alliance Surveying provided all survey services for the construction of the Roy Hill Rail flush butt yard. Work included:

  • Initial setup of a sold control network to enable an accurate baseline to construct the flush butt yard
  • Works began with Fremantle Constructions which included earthwork and concrete footing and pedestal setout and as constructed
  • Work continued with John Holland and included rail, steel fabrication modules and crane gantry setout and as constructed