Alliance Surveying provided Survey Services for the project, including site setout, machine control management and quantity calculations. Commenced in September 2013 the Marble Bar Road re-alignment was required due to the impact the Roy Hill Mine site had on the existing road alignment.

Work included:

  • 30km of road construction including, Marble Bar road North diversion, Village Access road and intersections