Alliance Surveying provided all surveying services for SRG for the design and construction of 2 x 5 mega litre storage tanks as part of the Onslow town water scheme.
The project included:
- All site earthworks which included clearing, temporary roads, set out for pre load of the site, detailed earthworks for tank construction, and 4.5km of road construction
- Set out and as constructed survey on pipeline connections to the town water supply
- Establishment and monitoring of earthworks settlement monitoring system from beginning of preload, removal of preload and during the construction of the concrete tanks
- Construction set out of the complex reinforced (post tensioned) concrete tanks
- Produce as constructed drawings for Water Corporation submission